Back to all reports

Failed surface

Reported via iOS in the Road Surface category anonymously at 14:52, Thursday 11 March 2021

Sent to Central Bedfordshire Council less than a minute later. Council ref: 353227.

The service road along Brookside Walk has a lot of pot holes. Some are fairly deep. The previous repairs have failed. The footpath along the service road AND at the front of Brookside Walk is also in a state of disrepair. The grass has not been cut back from the edges. This is causing the footpath to fail. There is a large fir tree in one of the Brookside Walk front gardens. The roots have lifted up the tarmac making a very interesting trip hazard. Hopefully action will be taken to make good the above faults.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • State changed to: Investigating

    Updated by Central Bedfordshire Council at 14:52, Thursday 11 March 2021

  • Thank you for your Highways report.
    An order has now been raised to rectify the identified issue and this will now be added to our programme of works. We are, unfortunately, unable to provide you with a timescale for this work to be completed, however, all repairs are prioritised using an assessment matrix in line with our Network Maintenance Management Plan (NMMP)

    We will continue to monitor all defects to ensure the safety of our residents as part of the NMMP which can be found online - http://www.centralbedfordshire.gov.uk/ transport/ roads-strategies/ highways-asset-management.aspx.

    Many thanks,
    Central Bedfordshire Council Highways.

    State changed to: Action scheduled

    Posted by Central Bedfordshire Council at 08:36, Thursday 18 March 2021

  • Still open, via questionnaire, 15:02, Thursday 8 April 2021

  • As expected, nothing has been done 🤷🏻‍♂️

    Posted anonymously at 15:31, Thursday 6 May 2021
    Still open, via questionnaire

  • As expected, nothing has been done .....

    State changed to: Open

    Posted by Central Bedfordshire Council at 15:32, Thursday 6 May 2021

  • Still not done!!!

    Posted by Central Bedfordshire Council at 16:33, Thursday 3 June 2021

  • Still not done!!!

    Posted anonymously at 16:33, Thursday 3 June 2021
    Still open, via questionnaire

  • Still open, via questionnaire, 18:04, Thursday 1 July 2021

  • The road has been patched.

    Posted by Central Bedfordshire Council at 18:59, Thursday 29 July 2021

  • The road has been patched.

    State changed to: Fixed

    Posted anonymously at 18:59, Thursday 29 July 2021

This report is now closed to updates. You can make a new report in the same location.