Damaged pavement outside 63 Elmwood Crescent

Reported via iOS in the Pavement and Cycle path category anonymously at 18:36, Wednesday 28 April 2021

Sent to Central Bedfordshire Council less than a minute later. Council ref: 355526.

The pavement which was dug up a few years ago has sunk and is very uneven. It’s directly outside my elderly parents’ home. Can this be looked into as a matter of urgency as I’m worried they’ll fall and injure themselves

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • State changed to: Investigating

    Updated by Central Bedfordshire Council at 18:36, Wednesday 28 April 2021

  • Can you please provide an update on this.

    State changed to: Open

    Posted by Central Bedfordshire Council at 18:28, Friday 21 May 2021

  • Can you please provide an update on this.

    State changed to: Investigating

    Posted anonymously at 18:28, Friday 21 May 2021

  • Still open, via questionnaire, 07:16, Sunday 30 May 2021

  • Still open, via questionnaire, 08:53, Sunday 27 June 2021

  • Thank you for your Highways report.
    Following you report we have carried out an inspection and raised an order to repair your identified issue and this has now been added to our programme of works.

    Many thanks,
    Central Bedfordshire Council Highways

    State changed to: Action scheduled

    Posted by Central Bedfordshire Council at 12:08, Friday 9 July 2021

  • Still open, via questionnaire, 16:27, Sunday 25 July 2021

  • Still open, via questionnaire, 17:04, Monday 23 August 2021

  • Questionnaire filled in by problem reporter

    State changed to: Open

    Posted by Central Bedfordshire Council at 17:33, Monday 20 September 2021

  • Questionnaire filled in by problem reporter

    State changed to: Fixed

    Posted anonymously at 17:33, Monday 20 September 2021

  • Thank you for your Highways report.

    We are currently assessing the report.

    Many thanks,Central Bedfordshire Council Highways, VA.

    State changed to: In progress

    Posted by Central Bedfordshire Council at 10:01, Tuesday 21 September 2021

  • Thank you for submitting your Highways report.

    These works have been completed.

    Many thanks,
    Central Bedfordshire Council Highways

    State changed to: No further action

    Posted by Central Bedfordshire Council at 12:34, Wednesday 22 September 2021

This report is now closed to updates. You can make a new report in the same location.