Closed
Large Pot Hole
Reported via iOS in the Potholes category anonymously at 16:52, Sat 8 January 2022
Sent to Central Bedfordshire Council less than a minute later. Council ref: 365582.
Large pot hole has opened up. Next to grass verge on Greenfields. Unable to avoid due to parked cars. When cars and lorries go over fast makes windows in house rattle. Needs sorting ASAP
Updates
-
State changed to: Investigating
Updated by Central Bedfordshire Council at 16:52, Sat 8 January 2022
-
Thank you for your Highways report.
We are currently assessing the report. If anything further is required, one of our engineers will contact you using the contact details provided.
Many thanks,
Central Bedfordshire Council HighwaysState changed to: In progress
Posted by Central Bedfordshire Council at 12:02, Tue 11 January 2022
-
Thank you for your Highways report.
Following you report we have carried out an inspection and raised an order to repair your identified issue and this has now been added to our programme of works.
An order has been raised to fill these holes whilst we await the more substantial works that are to happen on this road in the near future.Many thanks,
Central Bedfordshire Council Highways
State changed to: Action scheduled
Posted by Central Bedfordshire Council at 08:38, Wed 12 January 2022
-
Thank you for your Highways report.
Following you report we have carried out an inspection and raised an order to repair your identified issue and this has now been added to our programme of works.Many thanks,
Central Bedfordshire Council Highways
Posted by Central Bedfordshire Council at 15:05, Fri 14 January 2022
-
If fixing means jumping on some lose tarmac in the hole and hoping it stays in then no it.s not been fixed properly. Quite a few of the holes which have been filled in such a way have all reopened up Greenfields.
State changed to: Open
Posted by Central Bedfordshire Council at 17:36, Sat 5 February 2022
-
If fixing means jumping on some lose tarmac in the hole and hoping it stays in then no it’s not been fixed properly. Quite a few of the holes which have been filled in such a way have all reopened up Greenfields.
Posted anonymously at 17:36, Sat 5 February 2022
Still open, via questionnaire -
Thank you for your Highways report.
We have now inspected the defect and no planned repair is necessary at this stage. Please be assured that we will continue to monitor and inspect the road in line with our established service plan.
This was a temporary repair whilst we await the permanent works to commence.
Thank you for reporting this matter,
Central Bedfordshire Council HighwaysState changed to: No further action
Posted by Central Bedfordshire Council at 14:53, Tue 8 February 2022
This report is now closed to updates. You can make a new report in the same location.