Union Street Pavement both sides

Reported via desktop in the Pavement and Cycle path category anonymously at 16:26, Thursday 24 March 2022

Sent to Central Bedfordshire Council less than a minute later. Council ref: 369652.

Works have been completed to re-surface the pavement on Union Street

However the quality of the surfacing is poor compared to other resurfacing (First Avenue) It is nor level and even in places. The surface appears to be unfinished (a rough dressing) and of poor quality. Also in a number of cases the surfacing has encroached over the servie covers

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • State changed to: Investigating

    Updated by Central Bedfordshire Council at 16:26, Thursday 24 March 2022

  • Thank you for submitting your Highways report.
    The works completed on Union Street is a different surface treatment compared to the standard traditional repairs undertaken on First Avenue. Union Street was selected as a trial site for a slurry seal treatment, which is designed to extend the life of the existing surface by protecting it from ingress of water and the effects of freeze thaw. The rough texture is intensional as it helps slow down the deterioration of the original surface. Any encroached service covers will be revisited by our contractor and made accessible.
    No further action is required at this time.

    Many thanks,
    Central Bedfordshire Council Highways

    State changed to: No further action

    Posted by Central Bedfordshire Council at 14:17, Wednesday 30 March 2022

This report is now closed to updates. You can make a new report in the same location.