Pothole outside number 3
Reported via desktop in the Potholes category by Central Bedfordshire Council at 13:16, Mon 16 January 2023
Sent to Central Bedfordshire Council less than a minute later. Council ref: 381907.
Big pothole outside of house number 3
Updates
-
State changed to: Investigating
Updated by Central Bedfordshire Council at 13:16, Mon 16 January 2023
-
Customer called for updates.
I have advised the customer that there are 5 working days allocated for inspection only and after inspection the report will be updates.State changed to: Open
Posted by Central Bedfordshire Council at 10:58, Thu 19 January 2023
-
Customer called for updates as nothing happen yet.
Please can updates be provided as soon as possible?Email send to area team.
Posted by Central Bedfordshire Council at 13:40, Mon 30 January 2023
-
Costumer called again about this very upset because nothing is beeing done about this and she keeps needing to phone back , she also provided a phone number if someone could give ar a phone call with an update 01525211612
Thank you
Posted by Central Bedfordshire Council at 13:54, Mon 30 January 2023
-
Thank you for your Highways report.
We have now inspected the defect and no planned repair is necessary at this stage. Please be assured that we will continue to monitor and inspect the road in line with our established service plan.This will be reviewed in the new financial year
Thank you for reporting this matter,
Central Bedfordshire Council HighwaysState changed to: No further action
Posted by Central Bedfordshire Council at 07:51, Wed 8 February 2023
-
The customer would like this to be loolked intio urgently as the pot hole is getting worse and is very dangerous for them as it is outside her drive.
State changed to: Open
Posted by Central Bedfordshire Council at 13:02, Fri 10 February 2023
-
Thank you for your Highways report.
We have now inspected the defect and no planned repair is necessary at this stage. Please be assured that we will continue to monitor and inspect the road in line with our established service plan.To be reviewed in the new financial year
Thank you for reporting this matter,
Central Bedfordshire Council HighwaysState changed to: No further action
Posted by Central Bedfordshire Council at 14:50, Mon 13 February 2023
-
Customer called for updates. Customer did understood that this will be reviewed/fixed in the new financial year but wanted to ask if there is a possibility for this pothole to be covered even provisionally till fully sorted.
Customer finds it difficult to go in and out the drive way without hitting the pothole.
Customer will apreciate any support and action taken regarding this pothole. Customer said that the pothole is quite big and a bit surprised that was advised that no works are planned at the moment.State changed to: Open
Posted by Central Bedfordshire Council at 13:36, Tue 21 February 2023
-
Thank you for your Highways report.
We have now inspected the defect and no planned repair is necessary at this stage. Please be assured that we will continue to monitor and inspect the road in line with our established service plan.To be reviewed in the new financial year
Thank you for reporting this matter,
Central Bedfordshire Council HighwaysState changed to: No further action
Posted by Central Bedfordshire Council at 15:57, Mon 27 February 2023
-
Costumer has called again about this , to let us know that due to the weather the pothole has no gone bigger , can someone please inspect
Thank you
State changed to: Open
Posted by Central Bedfordshire Council at 12:59, Thu 9 March 2023
-
customer called sayin that the pothole is causing damage to their vehicle and it needs to be fixed. customer is very angry that she was told that it will investigated and monitored but it causing a lot of damage to them and they are also going out every now and then to cover the pothole so they can use the road, but its not helping matters for them.
Posted by Central Bedfordshire Council at 13:41, Mon 13 March 2023
-
Resident called again chasing this one, says it is causing damage to vehicles and that some are swerving to avoid it. Called through to area officer then emergency team to investigate
Posted by Central Bedfordshire Council at 11:57, Thu 23 March 2023
-
Thank you for your Highways report.
We are currently assessing the report. Please contact the customer for a photo. area Team have been contacted by yourselves. Please attach photo to CRN and let us know when this is done.
Many thanks,
Central Bedfordshire Council HighwaysState changed to: In progress
Posted by Central Bedfordshire Council at 13:19, Thu 23 March 2023
-
Call from customer Susan Tingey - claims this is now her 9th call to us- she is very frustrated and dissappointed that this pot hole has not been addressed- she feels this poses a real risk especially if encountered by a cyclist. she has chased this multiple times but to no avail- i have advised her i will chase this up with another GN11 and email the team direct to escalte. she wants this inspected again and made safe.
State changed to: Open
Posted by Central Bedfordshire Council at 13:15, Tue 4 April 2023
-
escalated to area team- area team escalated to e,ergency contractors
Posted by Central Bedfordshire Council at 14:26, Tue 4 April 2023
Only the original reporter may leave updates. If you made the original report please log in to leave an update.