In progress
Outside Britannia Pharmacy, 4 Market Square, Sandy, SG19 1HU.
Reported via desktop in the Drains/Ditches Blocked category anonymously at 12:28, Wednesday 15 November 2023
Sent to Central Bedfordshire Council less than a minute later. Council ref: 397067.
Dear Sirs, On 13th of October, we reported a blocked drain outside of our pharmacy, and also attached photographs of the blocked drain. After considerable delays, we had an update, that a local team has inspected the drain and they require heavy machinery to clear the drains, and that this will be done by a different team. We have been chasing for this, and on Friday, the 10th of November, there was an update on this platform, as below, indicating that the drain has been cleared. None of our staff, witnessed the team having been to the site, and hence we engaged a drain clearance company to confirm that the drains have been cleared. This was done yesterday morning, and we have confirmation with photographic evidence that the drain has not been cleared. The latest photos are attached. We have serious flooding issues during heavy rains and is imperative that the subject drain is cleared as a matter of urgency.
Below report from the earlier update:
Thank you for submitting your Highways report. The gully clearance and check has been completed, we will keep check on the flow of water on the next rainfall. Our engineers have inspected the area and are satisfied that no further action is required at this time. Many thanks, Central Bedfordshire Council Highways State changed to: No further action Posted by Central Bedfordshire Council at 11:40 today •
Updates
-
State changed to: Investigating
Updated by Central Bedfordshire Council at 12:28, Wednesday 15 November 2023
-
Please see photos attached.
Gurdev Channa 07 973 175 008
[ This update contains a photo, see: https://fixmystreet.centralbedfordshire.gov.uk/ photo/ c/ 12217296.0.full.jpeg?007be030 ]
State changed to: Open
Posted by Central Bedfordshire Council at 12:33, Wednesday 15 November 2023
-
Customer called as is desperate and pleading for this issue to be resolved. Email sent to Higways Liason Team.
Posted by Central Bedfordshire Council at 12:19, Monday 20 November 2023
-
Thank you for contacting us with information relating to a Highways issue. We plan to inspect the site during the next instance of significant rainfall (that takes place during working hours) and decide on the best course of action.
State changed to: In progress
Posted by Central Bedfordshire Council at 11:48, Tuesday 21 November 2023
-
Dear Sirs,
We wish to advise you that further to receiving a detailed email from Darren Foley, explaining the works within the highways department, we have responded to Darren , requesting to ensure that the correct gully is been referred to in his response to us.
In the event that the gully that Darren refers to is different from the subject gully, then further action will need to be taken swiftly.
Kind regards,
Gurdev Channa
State changed to: Open
Posted by Central Bedfordshire Council at 13:51, Tuesday 21 November 2023
-
Dear Sirs,
We wish to advise you that further to receiving a detailed email from Darren Foley, explaining the works within the highways department, we have responded to Darren , requesting to ensure that the correct gully is been referred to in his response to us.
In the event that the gully that Darren refers to is different from the subject gully, then further action will need to be taken swiftly.
Kind regards,
Gurdev Channa
State changed to: In progress
Posted anonymously at 13:51, Tuesday 21 November 2023