Action scheduled
Outside 37 & 39 Dunstable Road
Reported via desktop in the Surface water on Highway category anonymously at 06:56, Tue 28 November 2023
Sent to Central Bedfordshire Council less than a minute later. Council ref: 397597.
Road has been flooded virtually both sides for the past 2-3 weeks, this becomes treacherous when frosty/frozen conditions. If not cleared then a serious accident will occur as once frozen the water is then tracked further along the road in both directions
Updates
-
State changed to: Investigating
Updated by Central Bedfordshire Council at 06:56, Tue 28 November 2023
-
This has now frozen over resulting in lethal driving conditions. This has been an ongoing issue for approx 4 weeks & given the speed of the cars going through the village they are hitting the iced road surface with no hope of stopping
State changed to: Open
Posted by Central Bedfordshire Council at 07:13, Fri 1 December 2023
-
This has now frozen over resulting in lethal driving conditions. This has been an ongoing issue for approx 4 weeks & given the speed of the cars going through the village they are hitting the iced road surface with no hope of stopping
State changed to: Investigating
Posted anonymously at 07:13, Fri 1 December 2023
-
05.12.23 the road is completely flooded both side & now includes both pavements & there is now pedestrian access available from this end of the village as it is completely blocked, likewise cyclists will also have trouble riding through the flooding as at least a foot deep & the deepest point
Posted anonymously at 12:10, Tue 5 December 2023
-
05.12.23 the road is completely flooded both side & now includes both pavements & there is now pedestrian access available from this end of the village as it is completely blocked, likewise cyclists will also have trouble riding through the flooding as at least a foot deep & the deepest point
State changed to: Open
Posted by Central Bedfordshire Council at 12:11, Tue 5 December 2023
-
Thank you for your Highways report.
We have inspected the defect and carried out works to make the issue safe. Any further repairs that are needed will be completed in line with the timeframes set out in our maintenance plan.
Many thanks,
Central Bedfordshire Council HighwaysState changed to: Fixed
Posted by Central Bedfordshire Council at 11:23, Tue 12 December 2023
-
Thank you for your Highways report.
Following you report we have carried out an inspection and raised an order to repair your identified issue and this has now been added to our programme of works.Many thanks,
Central Bedfordshire Council Highways
State changed to: Action scheduled
Posted by Central Bedfordshire Council at 12:43, Friday 9 February 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.