Public footpath between 15 the green and The green man

Reported via desktop in the Public Rights of way category anonymously at 20:55, Tuesday 18 August 2026

Sent to Central Bedfordshire Council 1 week, 18 hours, 11 minutes later. Council ref: 17838.

I am contacting you to raise concerns regarding recent works to Public Footpath No. 2 in Clophill, forming the pedestrian route between Beverley Court and the High Street.

This is a particularly well-used public right of way. It provides an important pedestrian connection for residents of Beverley Court, many of whom are elderly, as well as the wider community, and is regularly used as a main walking route to access the shop at The Green and other local amenities.

Our immediate concern is that the adjoining landowner/developer has recently laid a loose gravel surface over the route of the public footpath.

The loose gravel has, in our view, made the path considerably less suitable for pedestrians and particularly difficult for wheelchair users, people with limited mobility, those using mobility aids, and parents or carers with pushchairs. Given the frequency with which this route is used by local residents, we do not believe loose gravel of this nature provides an appropriate or accessible surface for this public footpath.

We are also concerned that, during the week commencing 10 August 2026, the public footpath appears to have been closed to enable works to take place. We believe this closure may have been undertaken without the necessary authorisation.

These works appear to relate to Planning Application CB/26/00472/FULL – Land to the rear of The Green Man, The Green, Clophill, on which you previously provided Rights of Way consultation comments.

We note that your comments on that application specifically stated that: “The legal line of Public Footpath no. 2 should remain completely unaffected by any proposals and the route should remain safe to use by the public.”

You also specifically recognised the importance of this route, describing it as: “a very well used route, particularly for residents of Beverley Court.”

Those comments are particularly relevant to our current concerns. The apparent closure of the footpath during the works, followed by the installation of a loose gravel surface which has made the route more difficult for sections of the community to use, would appear to be inconsistent with the expectation that the legal line remains unaffected and safe to use by the public.

We would therefore be grateful if Central Bedfordshire Council’s Public Rights of Way team could inspect the footpath and advise on the following:

Whether the temporary closure of Public Footpath No. 2 during the week commencing 10 August was authorised. Whether the laying of loose gravel over the public right of way was authorised or agreed with the Council. Whether the current loose gravel surface is considered suitable for such a frequently used public footpath, particularly given its use by elderly residents, wheelchair and mobility-aid users and people with pushchairs. Whether these works comply with the requirements and considerations raised by the Rights of Way team in relation to planning application CB/26/00472/FULL. If the works or closure were not authorised, or the surface is considered to have unreasonably affected public access, what action can be taken to require the route to be reinstated or improved to provide a safe, firm and suitably accessible pedestrian surface. I want to stress that the intention is not to object unnecessarily to legitimate improvements or maintenance undertaken by the landowner. The concern is that works associated with a development should not result in an established and heavily used public right of way becoming less accessible than it was previously, particularly when it provides an important route for elderly and less-mobile members of the community.

Updates

  • State changed to: Investigating

    Updated by Central Bedfordshire Council at 15:06, Wednesday 26 August 2026

  • Thank you for your query. We will get back to you.

    Category changed from ‘Pavement and Cycle path’ to ‘Public Rights of way’

    Posted by Central Bedfordshire Council at 12:00, Thursday 27 August 2026